CFE’s OM vs HM vs H-MT tariff: when each one suits you (with a real calculation)

Tarifa OM vs HM vs H-MT de CFE: cuándo cada una te conviene (con cálculo real)

OM and HM exist, but under a new name; H-MT does not appear as a category in the current tariff schedule.

The agreement of the National Energy Commission (CNE) that governed 2026 tariffs includes the equivalence table with CFE’s previous scheme: GDMTO (Gran Demanda en Media Tensión Ordinaria) corresponds to OM; GDMTH (Gran Demanda en Media Tensión Horaria) to HM and HMC; DIST and DIT, high voltage, formerly HS and HT. H-MT appears neither there nor in CFE’s table.

What exists are two tariffs whose name does not reveal their requirement: GDMTO, low load in medium voltage, and GDBT, large demand in low voltage above 25 kW-month. Publishing H-MT as a third option would be inventing it.

ConceptOM, today GDMTOHM, today GDMTHH-MT
Current categoryGDMTO (formerly OM)GDMTH (formerly HM)Does not exist
Demand that appliesLess than 100 kWEqual to or greater than 100 kWNot verified
Voltage levelMedium voltageMedium voltageNot verified
Energy priceA single priceBase, intermediate and peakNot verified
Demand chargesCapacity and distribution, $/kWCapacity and distribution, $/kWNot verified
Load factor0.550.57Not verified
Tariff jumpIn the third month above 100 kW, CFE reclassifies to GDMTHAfter 12 months below 100 kW, GDMTO is requestedNot verified

What decides your tariff: 100 kW

GDMTO applies to services of any use in medium voltage with demand below 100 kW; GDMTH, to the same services with demand equal to or greater than 100 kW per month. Contracted demand cannot be less than 60% of the total connected load, nor less than 100 kW in GDMTH, nor less than 10 kW in GDMTO.

If the maximum measured demand equals or exceeds 100 kW, the user must request GDMTH; if it does not, in the third consecutive month CFE reclassifies it, and returning requires 12 consecutive months below 100 kW. For a data center that is a tautology: a 3 or 5 MW site sits 30 or 50 times above the threshold.

The three layers of the bill

  • Fixed supply charge: a monthly fee independent of consumption, for metering, billing and customer service.
  • Energy: a charge per kilowatt-hour (kWh) consumed; in GDMTH it is split into three time blocks (base, intermediate and peak) according to the season and the tariff division.
  • Demand: monthly charges in $/kW for capacity (generation available during peak hours) and distribution (use of the general distribution networks), calculated on the maximum measured or billable demand.
  • The security deposit is twice the capacity charge per contracted kilowatt: $3,771,649 for 5 MW.

    The real calculation: 5 MW in the Bajío division

    The scenario: a data center with 5,000 kW of contracted demand in medium voltage, flat consumption and a load factor of 0.85: 3,060,000 kWh in 30 days. In November the winter schedule of the National Interconnected System applies: 248 base hours, 380 intermediate and 92 peak. The split is 1,054,000 kWh base, 1,615,000 intermediate and 391,000 peak.

    Billable demand is the minimum between the 5,000 kW measured and 3,060,000 kWh divided by 0.57 and 720 hours, which gives 7,456 kW. The peak wins: 5,000 kW.

    With the CNE charges for November 2026 in Bajío:

  • Energy: 1,054,000 × 1.0228 + 1,615,000 × 1.8107 + 391,000 × 2.0620 = $4,808,578.
  • Capacity: 5,000 kW × 377.1649 $/kW = $1,885,824.
  • Distribution: 5,000 kW × 97.88 $/kW = $489,400.
  • Fixed charge: $427.19.
  • Subtotal before VAT: $7,184,230. With 16% VAT: $8,333,707 per month.
  • Annualized at November 2026 prices that is about $100.0 million a year, or $2.7234 per kWh with VAT. Demand accounts for 33.1% of the subtotal.

    If the same load were paid as GDMTO

    Warning: the comparison is arithmetic, not contractual. CFE does not allow 5 MW to be billed under GDMTO, because that category is for less than 100 kW. It serves to size the cost of the hourly structure with immovable load.

    With the ordinary structure, a single price of 1.4871 $/kWh, capacity of 324.69 $/kW and the same distribution charge, the month would come to $7,729,901 with VAT: $603,806 less, about $7.2 million a year. That is the price of penalizing peak consumption: a data center draws the same 24 hours a day.

    Peak hours, 12.8% of the month, contribute 16.8% of the energy and cost twice as much as base. For an industrial plant that is an invitation to shift processes; for a data center there is nowhere to shift them.

    What you can actually move

  • The peak, not the volume: use battery banks (BESS) or on-site generation to trim maximum demand during the month’s 92 peak hours (peak shaving) and reduce the capacity charge.
  • Contracted demand: adjust the contract to the actual load projected by stages, so as not to tie up excessive capital in the security deposit or pay for underused capacity.
  • The purchasing regime: if your site exceeds 1 MW of demand, evaluate registering as a Qualified User to negotiate power hedge contracts with qualified suppliers outside CFE’s basic supply.
  • Of the three tariffs in the headline, only one is real for a medium-voltage data center: HM, today GDMTH. And it is not chosen by its name, it applies by its demand.

    Sources

  • CNE agreement (DOF, April 2026): 100 kW threshold, load factors and tariff equivalence. https://dof.gob.mx/nota_detalle.php?codigo=5783862&fecha=01/04/2026
  • Calculation memorandum of the Basic Supply Final Tariffs (November 2026): charges by division. https://www.cne.gob.mx/da/Memorias%20de%20c%c3%a1lculo%20de%20tarifas%20finales%20del%20Suministro%20B%c3%a1sico/2026/Noviembre%202026/TarifasFinalesdeSuministroBasico2026.xlsx
  • CFE’s current tariff scheme: equivalence of the twelve current categories, without H-MT. https://app.cfe.mx/Aplicaciones/CCFE/Tarifas/TarifasCREIndustria/Industria.aspx
  • CFE’s GDMTH tariff datasheet: schedules, capacity and distribution charges and deposit. https://app.cfe.mx/Aplicaciones/CCFE/Tarifas/TarifasCRENegocio/Tarifas/GranDemandaMTH.aspx
  • Regulations of the Electric Sector Law: 1 MW for Qualified User and 5 MW for the Wholesale Electricity Market. https://www.diputados.gob.mx/LeyesBiblio/regley/Reg_LSE.pdf
  • Want to master this?

    Noxtel Academy →

    Also in Energy and Sustainability

    ← Back to categories