CFE’s OM vs HM vs H-MT tariff: when each one suits you (with a real calculation)
OM and HM exist, but under a new name; H-MT does not appear as a category in the current tariff schedule.
The agreement of the National Energy Commission (CNE) that governed 2026 tariffs includes the equivalence table with CFE’s previous scheme: GDMTO (Gran Demanda en Media Tensión Ordinaria) corresponds to OM; GDMTH (Gran Demanda en Media Tensión Horaria) to HM and HMC; DIST and DIT, high voltage, formerly HS and HT. H-MT appears neither there nor in CFE’s table.
What exists are two tariffs whose name does not reveal their requirement: GDMTO, low load in medium voltage, and GDBT, large demand in low voltage above 25 kW-month. Publishing H-MT as a third option would be inventing it.
| Concept | OM, today GDMTO | HM, today GDMTH | H-MT |
|---|---|---|---|
| Current category | GDMTO (formerly OM) | GDMTH (formerly HM) | Does not exist |
| Demand that applies | Less than 100 kW | Equal to or greater than 100 kW | Not verified |
| Voltage level | Medium voltage | Medium voltage | Not verified |
| Energy price | A single price | Base, intermediate and peak | Not verified |
| Demand charges | Capacity and distribution, $/kW | Capacity and distribution, $/kW | Not verified |
| Load factor | 0.55 | 0.57 | Not verified |
| Tariff jump | In the third month above 100 kW, CFE reclassifies to GDMTH | After 12 months below 100 kW, GDMTO is requested | Not verified |
What decides your tariff: 100 kW
GDMTO applies to services of any use in medium voltage with demand below 100 kW; GDMTH, to the same services with demand equal to or greater than 100 kW per month. Contracted demand cannot be less than 60% of the total connected load, nor less than 100 kW in GDMTH, nor less than 10 kW in GDMTO.
If the maximum measured demand equals or exceeds 100 kW, the user must request GDMTH; if it does not, in the third consecutive month CFE reclassifies it, and returning requires 12 consecutive months below 100 kW. For a data center that is a tautology: a 3 or 5 MW site sits 30 or 50 times above the threshold.
The three layers of the bill
The security deposit is twice the capacity charge per contracted kilowatt: $3,771,649 for 5 MW.
The real calculation: 5 MW in the Bajío division
The scenario: a data center with 5,000 kW of contracted demand in medium voltage, flat consumption and a load factor of 0.85: 3,060,000 kWh in 30 days. In November the winter schedule of the National Interconnected System applies: 248 base hours, 380 intermediate and 92 peak. The split is 1,054,000 kWh base, 1,615,000 intermediate and 391,000 peak.
Billable demand is the minimum between the 5,000 kW measured and 3,060,000 kWh divided by 0.57 and 720 hours, which gives 7,456 kW. The peak wins: 5,000 kW.
With the CNE charges for November 2026 in Bajío:
Annualized at November 2026 prices that is about $100.0 million a year, or $2.7234 per kWh with VAT. Demand accounts for 33.1% of the subtotal.
If the same load were paid as GDMTO
Warning: the comparison is arithmetic, not contractual. CFE does not allow 5 MW to be billed under GDMTO, because that category is for less than 100 kW. It serves to size the cost of the hourly structure with immovable load.
With the ordinary structure, a single price of 1.4871 $/kWh, capacity of 324.69 $/kW and the same distribution charge, the month would come to $7,729,901 with VAT: $603,806 less, about $7.2 million a year. That is the price of penalizing peak consumption: a data center draws the same 24 hours a day.
Peak hours, 12.8% of the month, contribute 16.8% of the energy and cost twice as much as base. For an industrial plant that is an invitation to shift processes; for a data center there is nowhere to shift them.
What you can actually move
Of the three tariffs in the headline, only one is real for a medium-voltage data center: HM, today GDMTH. And it is not chosen by its name, it applies by its demand.