CloudHQ in Querétaro: what the 900 MW announcement does say and what it hides about CFE, water and the 2027 timeline

CloudHQ en Querétaro: lo que el anuncio de 900 MW sí dice y lo que esconde sobre CFE, agua y el timeline 2027

When on September 25, 2025 President Claudia Sheinbaum presented, alongside Marcelo Ebrard and Keith Patrick Harney, CloudHQ COO, the 4,800 million dollar project to build six data centers on 52 hectares near Querétaro International Airport, the most repeated figure was 900 MW of critical IT load. For the Mexican investor weighing whether that announcement changes his roadmap, that figure is fine — but it is not the most important one. The figure that changes decisions is the other one: 200 MW secured today with CFE and CENACE, inside a 1,705 MW sector commitment that the September 10, 2026 CFE–MEXDC agreement has only just started to route.

In this article we break down the 5 points of the announcement that your CFO should not read as marketing.

What the announcement does say (verifiable)

The official press release from the Secretaría de Economía (Plan México, gob.mx, September 2025) confirms four hard data points that require no reinterpretation:

Hard data point from the official releaseValue
Investment4,800 million dollars, spread across six buildings
Surface area52 hectares in Querétaro, adjacent to the International Airport
Critical IT load900 MW, with a dedicated private substation and a 2 GW maneuvering substation
Secured capacity200 MW with CFE and CENACE support, with prior investment of 250 million dollars

Plus two operational commitments:

  • 7,200 direct jobs during construction, 900 permanent once operational.
  • Waterless cooling (closed-loop liquid cooling), with LEED gold and silver certifications.
  • That is all verifiable. What the announcement does not say — and that is what your team will have to cross-check — is the real speed of energization per block, the delivery schedule for the dedicated 400 kV substation, and the fallback path if the 2 GW maneuvering substation is delayed. We answer those three questions in the next section using the public information available as of October 2026.

    What it does not say: CFE, CENACE and the 2027 window

    The agreement signed on September 10, 2026 between the Comisión Federal de Electricidad (CFE) and the Asociación Mexicana de Centros de Datos (MEXDC) is the piece that turns the CloudHQ announcement from a promise into a technical roadmap. It recognizes three things that change your sign-up:

  • 1,705 MW of demand already identified by the industry at various stages.
  • 279 MW installed today, with 205 MW under construction during 2026.
  • Projection of 1.73 GW required towards 2031 — 6.2 times the current installed base in under six years.
  • The agreement establishes three pilots in Polos de Desarrollo to test the CFE-project coordination model before scaling it. In practice: if CloudHQ delivers the 200 MW secured today, the next block enters the review queue project by project, not as an automatic promise. That queue is the one that gets congested — Querétaro accumulates 298.2 MW of inventory in Q1 2026 according to CBRE, with 450.2% year-over-year growth, the highest in Latin America, and 10.6% vacancy (from 0.9% the previous year). Vacancy rose because the CFE grid does not absorb supply at the rate hyperscalers announce capacity.

    Why waterless cooling matters more than it appears

    CloudHQ did not choose waterless cooling for ESG marketing. It chose it because Querétaro already has documented water stress and approval of new sites will be conditioned on WUE (Water Usage Effectiveness). The data point that usually does not show up in reports: the Querétaro–San Miguel de Allende–Celaya corridor is in a medium-high water stress zone according to CONAGUA, and projects that use municipal water for evaporative cooling will face permitting restrictions before SEMARNAT in 2027. CloudHQ got ahead of the regulatory framework that is coming.

    Implication for your project: if you are evaluating a brownfield in Querétaro, Monterrey or CDMX and your design uses evaporative cooling towers or chillers with municipal water consumption, WUE and SEMARNAT approval will get complicated regardless of site size. Closed-loop liquid cooling with a CDU (Coolant Distribution Unit) paired with a dry cooler is the route CloudHQ validated as bankable on Mexican soil.

    CFE-MEXDC 1,705 MW: the real map of capacity by region

    The 1,705 MW figure is not a promise — it is a commitment signed between the industry and the grid operator. What that figure hides is the geographic distribution. What we know as of October 2026 from regional coverage:

  • Querétaro concentrates 298.2 MW of inventory (Q1 2026, CBRE) and is the largest hub in Mexico.
  • Monterrey is the second pole with accelerated growth (Nuevo León) and the highest CFE capacity per capita of industry.
  • CDMX has the most robust grid in the country, but land costs and regulatory constraints make it less competitive for hyperscale greenfield.
  • Apodaca, San Luis Potosí and Jalisco emerge as alternative corridors because of Querétaro saturation.
  • For an enterprise project between 5 and 50 MW, the question is no longer “which state suits me better?” but “which specific CFE substation can I connect my load to, and in which 18-month window?”. That granularity is not in the CloudHQ announcement; CFE answers it project by project under the new scheme.

    What it means for your 2027–2028 sign-up

    CloudHQ confirmed a full 2027 energization window. That puts pressure on three schedules:

  • Your site selection RFP closes in Q1 2027 if you want to move in the same window as hyperscaler demand.
  • Your CFE application under the new project-by-project scheme must be filed no later than Q1 2027 to enter the review blocks of the first half of that year.
  • Your MEP design must assume waterless cooling as the default, not as an option, if you want to avoid re-permitting risk in 2027.
  • The 5 questions your CFO will have to answer before signing with any colocation or hyperscaler in Mexico in this cycle:

  • Which specific CFE block is already assigned to this site and what is the contractual energization date, as opposed to the announced one?
  • Does the design use closed-loop liquid cooling or evaporative towers, and who pays for the retrofit if the regulator requires WUE below 0.5 before 2028?
  • Does the site have a dedicated substation or share infrastructure with other tenants, and what is the fallback agreement in case of curtailment?
  • Does the CFE-MEXDC agreement cover this specific site or is it a generic statement with no capacity guarantee?
  • What is the contractual agreement if CloudHQ (or the colocation you choose) delays energization beyond 2027?
  • The short answer: if your provider does not hand you documentary evidence — not press releases — on these five points, your risk is not technological, it is schedule.

    Verdict

    CloudHQ in Querétaro is the largest project announced in Mexico in 2025–2026 and Sheinbaum’s 2026 bet to reposition the country on the hyperscale AI factory map. The 900 MW figure is real, the 4,800 million dollar investment is real, and the 2027 window is a signed commitment. What is still an open question — and where your CFO carries the largest risk — is how the next 700 MW of CloudHQ get routed in the 1,705 MW CFE-MEXDC queue, and how that same bottleneck affects your own sign-up if your site falls in the Querétaro corridor.

    If you are interested in auditing your brownfield project in Mexico under the new 1,705 MW CFE-MEXDC + WUE + dedicated substation framework, request a site assessment with Noxtel — we deliver a 6-page memo with the technical, regulatory and financial path specific to your load.


    Sources

  • Secretaría de Economía / Government of Mexico. “Plan México avanza: Se anuncia inversión de 4 mil 800 mdd de CloudHQ para la construcción de 6 Centros de Datos en Querétaro”. gob.mx/presidencia, 2025-09 — https://www.gob.mx/presidencia/prensa/plan-mexico-avanza-se-anuncia-inversion-de-4-mil-800-mdd-de-cloudhq-para-la-construccion-de-6-centros-de-datos-en-queretaro
  • CBRE. “Global Data Center Trends 2026 — Querétaro: 298.2 MW inventory, +450.2% YoY, vacancy 10.6%”. 2026-Q1 — https://www.cbre.com/insights/reports/global-data-center-trends-2026
  • Remio. “Sheinbaum Backs Mexico's Data Center Ambition, but Power Remains the Constraint”. 2026-09-30 — https://remio.ai/post/sheinbaum-backs-mexicos-data-center-ambition-but-power-remains-the-constraint
  • Energía Estratégica. “CFE y la industria de data centers acuerdan una ruta para atender 1,705 MW de nueva demanda en México”. 2026-09-10 — https://energiaestrategica.com/en/notes/cfe-y-la-industria-de-data-centers-acuerdan-una-ruta-para-atender-1705-mw-de-nueva-demanda-en-mexico
  • The Watt. “CFE and MEXDC Agree on Joint Planning for 1.73 GW of Data Center Capacity”. 2026-09-10 — https://thewatt.org/en/nota/cfe-mexdc-data-center-grid-planning
  • Want to master this?

    Noxtel Academy →

    Also in Energy and Sustainability

    ← Back to categories